Construct onshore electrical transmission infrastructure comprising of a cable transition jointing bay, underground cable circuits, construction of substation to south of Keith with further connecting cabling to allow connection with existing transmission network at Blackhillock including temporary construction compounds, access track laydown areas and other associated works from within the vicinity of Redhythe Point in Aberdeenshire Council area to Whitehillock Farm, Keith, Moray for Moray Offshore Windfarm (West) Limited.